> From: Mark Aho <<email obscured>>
> Subject: The Bessemer - Owner/Architect/Neighbor Update - 1/08/21
> Date: January 8, 2021 at 2:08:42 PM CST
>
>
> Happy New Year ! β Already one week inβ¦
>
> This week at The Bessemer β
> Bolander worked along side of the plumbers (3D Mechanical) electricians
(Medina) and flat workers (DRF) to complete the radon mitigation system as well
as the final grade of the lower level garage .
>
> Next week at The Bessemer β
> Starting right away on Monday morning, DRF will start to pour the lower level
garage slab. Half will be poured on Monday and the next half will be poured on
Tuesday. All of this concrete will be carted in by power wheel barrows. Tuesday
wall panels for the 1st floor will show up and start to install. Bolander will
be back onsite on Wednesday to complete the foundation backfill.